    Hi, 

    I'm currently trialling Allocatus for my project team, but wish them to link back their own 'non project' time to project server, so that it shows as busy (and that they are not available in the resource pool).

    However, how best to do this? Do I create an 'individual' project for each person?  – Then get them to link outlook entries to this? Would this work? What is the recommended way please? It would be excellent to have (say) a few categories such as 'office' holiday etc that they can link many Outlook appointments to as they need to in Outlook.

    Many Thanks! 

    Last modified on 18 May 2016 19:05 by aniko.erlinger
  2. admin
    admin avatar
    209 posts
    Registered:
    09 Aug 2015
    Answered
    11 Aug 2015 in reply to user
    Link to this post

    Hi,

    the exact configuration depends on your requirements. Typically you would setup an absence project with a task for each category and assign your team members as resources to it. The team members can then use the Link to Project feature in Outlook desktop version to assign an existing appointment to a task in the absence project.

    Please discuss your scenario with our support team. They will send your a custom Admin Guide with the required settings, provide your the Allocatus Client Setup that enables the Link to Project Feature in Outlook.