admin
209 posts
Registered:
09 Aug 2015
26 Jul 2016
in reply to
user
Link to this post
All assignments, where the current
user is the assignment owner but not the resource itself are always displayed
as All Day events to distinguish them from tasks of the actual user.
Changing this behaviour would
require changing the underlying functionality.
Consider using the following option,
or any others that remove the assignments from being available in your Tasks
page:
Set Publihed = No in Project client
Set Booking type to proposed
Change assignment owner
Would any of
those options work for you?