    In the event that you try to schedule someone on a project and they already have something scheduled on their calendar, how does the application handle schedule conflicts?

    Last modified on 18 May 2016 20:05 by aniko.erlinger
  2. admin
    admin avatar
    209 posts
    Registered:
    09 Aug 2015
    Answered
    11 Aug 2015 in reply to user
    Link to this post

    With the AutoLink option enabled Allocatus creates for each assignment in MS Project an appointment in the calendar. If the team member assigns existing appointments to tasks in MS Project (Link to Project button in Outlook), the project manager can avoid scheduling conflicts before publishing the tasks.

    Last modified on 18 May 2016 20:05 by aniko.erlinger