Project tasks with generic resources assigned are displaying tasks in the calendar of the “Assignment Owner” as “All Day” events

2 posts, 1 answered
  1. user
    user avatar
    252 posts
    Registered:
    09 Aug 2015
    Answered
    26 Jul 2016
    Link to this post
    Project tasks with generic resources assigned are displaying tasks in the calendar of the “Assignment Owner” as “All Day” events. Can this be turned off?
  2. admin
    admin avatar
    209 posts
    Registered:
    09 Aug 2015
    26 Jul 2016 in reply to user
    Link to this post
    All assignments, where the current user is the assignment owner but not the resource itself are always displayed as All Day events to distinguish them from tasks of the actual user.

    Changing this behaviour would require changing the underlying functionality.
    Consider using the following option, or any others that remove the assignments from being available in your Tasks page:

    Set Publihed = No in Project client
    Set Booking type to proposed
    Change assignment owner

    Would any of those options work for you?