Handling Scheduling Conflicts with existing appointments

2 Beiträge, 1 beantwortet
  1. user
    user avatar
    252 Beiträge
    Mitglied seit:
    09 Aug 2015
    11 Aug 2015
    Auf diesen Beitrag verlinken

    In the event that you try to schedule someone on a project and they already have something scheduled on their calendar, how does the application handle schedule conflicts?

    Zuletzt bearbeitet am 18 Mai 2016 20:05 von aniko.erlinger
  2. admin
    admin avatar
    209 Beiträge
    Mitglied seit:
    09 Aug 2015
    Beantwortet
    11 Aug 2015 als Antwort auf user
    Auf diesen Beitrag verlinken

    With the AutoLink option enabled Allocatus creates for each assignment in MS Project an appointment in the calendar. If the team member assigns existing appointments to tasks in MS Project (Link to Project button in Outlook), the project manager can avoid scheduling conflicts before publishing the tasks.

    Zuletzt bearbeitet am 18 Mai 2016 20:05 von aniko.erlinger